Update Information
September 26,
2011 Capital Project Update
·
The Part l and Part ll of
the original project have been completed and the close
out of these initial projects is in progress.
·
On the first and second
floor hallways of the High School, the asbestos floor
tile was removed and replaced with new tiles this past
summer.
·
A portion of the roof on
the 1936 Wing in the Elementary Building was replaced
during the summer. The roof replacement is above the
Auditorium, classrooms and Pre-K room.
·
Some of the exterior
doors are scheduled to be replaced on both campuses this
fall.
·
Exterior lighting will be
installed this fall at the Ovid campus in the student
parking lot as well as the District Office parking lot.
Interior fire doors, on both campuses, will be replaced
during the summer of 2012.
|